Estimated Manpower Needed for Assembling the Aluminum Panel Formwork System

Estimated Manpower Needed for Assembling the Aluminum Panel Formwork System

It depends on various factors such as the complexity of the project, the size of the panels, and the experience of the labor force. However, general guidelines can help provide an estimate.

1.Typical Manpower Requirements

1.1Basic Team Structure:

Formwork Supervisor: 1 person

Laborers/Helpers: 6-10 persons

1.2.Standard Project Estimates:

Small to Medium-Sized Projects:

A team of approximately 6-10 workers can assemble and disassemble about 240-400 square meters of aluminum formwork per day per worker.

Large Projects:

Larger projects may require multiple teams working in parallel. For example, assembling 800-1200 square meters per day might need 20-30 workers, organized in several sub-teams under a lead supervisor.

2.Factors Influencing Manpower Requirements

-Panel Size and Weight:

Larger panels may require fewer but more skilled workers, as they cover more area per unit.

Smaller panels might be easier to handle but require more frequent adjustments and fittings, increasing the labor requirement.

-Project Complexity:

Projects with complex architectural designs or numerous variations in formwork shapes and sizes will need more skilled workers to manage the assembly efficiently.

-Experience and Training:

Experienced workers can assemble formwork more quickly and accurately, reducing the overall manpower required.

Proper training and familiarity with the aluminum panel system can significantly reduce assembly time and labor needs.

Share:
AluliteForms-logo

Alulite Forms – A professional company for designing, manufacturing and distributing construction formwork systems

Alulite Forms
Focus on construction formwork systems!

Ask For A Quick Quote!

We will contact you within 1 working day, please pay attention to the email with the suffix “@aluliteforms.com”